Corporate project · Darnel Group (Ajover)
The whole shift, one system
Logistics Leaders App
Problem
- The leaders' standard work had not been mapped or updated.
- Gemba walks, shift handovers and issues were managed outside any common system.
- Supervisors and managers had no real-time information about the operation.
- Related documentation —Gemba Wall, daily warehouse inspection procedure— was out of date.
Solution
- Leaders' Standard Work: mapping and updating the standard work.
- Gemba Walk: daily walks across 3 shifts, digitized in the app.
- Shift handover log, built into the same app.
- Management of issues raised during the Gemba walk, with follow-up.
- AI agent in Microsoft Copilot built on corporate procedures, work instructions, manuals and the knowledge of leaders, supervisors, managers and experts, to support planning, organizing and deciding during the shift.
- Documentation update: creation and update of the Gemba Wall and of the daily warehouse inspection procedure, among others.
Result
- Project in progress, partially in production.
- ~20 leaders in Cartagena as direct users, across three warehouses.
- Gemba walks digitized across the 3 daily shifts.
- Operational information available in real time to supervisors and managers.
- Status
- In progress
- Users
- ~20 leaders in Cartagena (~8 per warehouse in the two main warehouses, plus a smaller third one)
- Volume
- Gemba walks across 3 daily shifts
Technologies